Development

Project Tracker

Open progress on every community project — budgets, status and completion dates.

Project
Status
Progress
Complete
Nora River bridge repairs
Budget: USD 42,000
Ongoing
60%
Q4 2026
Ward 20 borehole rehabilitation
Budget: USD 18,000
Ongoing
35%
Q3 2026
Rusike Primary classroom block
Budget: USD 65,000
Completed
100%
2025
Rabbit co-op abattoir link
Budget: USD 22,000
Completed
100%
2025
Zunde raMambo grain silo
Budget: TBC
Planned
0%
2027
Solar mini-grid pilot
Budget: Seeking partners
Planned
0%
2027–28